» / References / DataCentres  / CEZ – BBCentrum - II.

Data centre of the company CEZ – II. stage

Investor:   ČEZData s.r.o.
Installation site:  BB Centrum, Prague 4
Delivery period:  03/2007 - 06/2007

The task:

  • to solve the project design and to deliver and install non-IT infrastructure for a new computer room of the companies CEZ and CEZData

Optimal approach:

  • the project solution of computer room floor plan and determination of necessary extent of construction adaptations in given, by the client appointed premises;
  • the delivery and installation of raised floors, racks, power distribution units, air-conditioning units, metallic and fibre-optic data networks;
  • the elaboration of the displacement project and connection of individual technology blocks to the power system infrastructure and to the structured data networks

Added value of realized concept:

  • ALTRON built a new computer room with an average power density 5kW per rack, and incorporated all individual elements of the network critical physical infrastructure into the monitoring system PROMON™, to be able to provide their permanent monitoring of operational parameters in scope of  the concluded CFM contract