Data centre Telefónica O2 - Chodov
Investor: Telefónica O2 Czech Republic
Installation site: Chodov, Prague 4
The task:
- to complete the 2nd stage of the data centre construction, to open 6 new computer rooms
Optimal approach:
- to enlarge the AC and DC power systems in terms of sophisticated concept, which was previously accepted in order to ensure data centre stepwise scalability;
- installation of all supportive technologies; execution of installation works in such a way that they do not cause any impact on existing data centre operation;
- delivery of UPS systems, the third genset, direct current power supplies and inverters, including their integration into the system
Added value of realized concept:
- ALTRON enlarged the monitoring system PROMON™ by newly installed technologies and incorporated the computer rooms into its non-stop remote monitoring system;
- ALTRON‘s cooperation with the client is long lasting - for this data centre ALTRON already provides complex Critical Facility Management services, namely since the start of the data centre’s operation;
- the six new computer rooms became the new milestone of successful cooperation